Work on the Betzdorf construction site is progressing! Currently, paving work is being carried out on the platform between tracks 106 and 107, extending to the platform edge. The planned commissioning is scheduled for week 40 of 2024. The staircase work is also advancing rapidly. The deconstruction has been completed, and the new construction, including formwork and concrete pouring, will take place in the coming weeks. The final block steps are planned to be installed in 2025.
This progress once again highlights HERING Bahnbau's expertise in civil engineering and infrastructure renewal.