With our newly developed Foundation Construction Train, we deliver safe, reliable, and cost-efficient foundation solutions — directly from the track, whether in station areas, on open lines, in cuttings, or on embankments.
Thanks to a specialized setup process, integrated tool logistics, and high foundation performance, this rail-based carrier unit combines proven special civil engineering methods with the unique requirements of railway construction — enabling sustainable, safe, and efficient project execution.
Overview of Technical Methods
Vibratory Driving
- Installation of sheet piles
and soldier pile walls - Max pile length: 15.0 m
- Reach: 9.4 m
Pressing (MPZ / MPU)
- Max pile length: 15.0 m
- Reach: 9.0 m
Impact Driving (using HRS 5)
- Hammer weight: 5 t
- Max pile length: 12.2 m
- Reach: 9.4 m
Drilling
- Installation of bored piles
up to 18.0 m depth - Diameter up to 1,350 mm
- Reach up to 9.5 m
Applications
We build foundations where crawler equipment can’t reach!