Back in 2019, the central platform at tracks 2 and 3 was extended by 118 meters using our modula® flex and light system. This year, the platform at track 2 was extended by another approximately 22 meters. What makes this project special: one already-installed modula® light slab, previously located at the end of the original platform, was removed and reinstalled at the new platform end. This allowed us to save an additional slab and contribute to resource conservation.
The installation work was carried out in calendar week 18. Our client was Reif Bauunternehmung, with whom we once again collaborated successfully and in a spirit of partnership.