Build the formwork structure in a side position and slide it into its final position. Partially demolish the old wing walls and secure them with grout anchors. Create reinforcements and pour concrete for the frame structure in its final position.
DB Netz AG, Münster
06/2023 - 02/2025
Approx. €0.8 million
Structure
Quantities
Install two temporary bridges, each 24 meters long.
Build the formwork structure in a side position and slide it into its final position.
Bridge type rolled girder in concrete
Bridge type with steel superstructure
Frame structure for a railway overpass
Frame structure for railway overpass
Installation of two auxiliary bridges