Demolition work on the old station and the associated area on behalf of DB-Station&Service AG and MTB Nordstemmen (the general contractor) started at the beginning of June 2023.
The HERING Systeme team also did a great job on this project – it was responsible for the planning, manufacture and delivery of the new platforms. The modula® 1b system platforms were installed on special prefabricated pile head beams using a mobile crane to ensure the necessary stability, safety and durability.
The project’s 2.75-metre-wide platform elements stretched to a total length of 70 metres. The height from the top of the rail is 38 centimetres. Delivery was by standard truck semi-trailer, with the exception of one 3.25-metre-wide element, which needed to be transported to the construction site at an angle by inloader truck.