... and the Niederrad junction in Frankfurt
The colleagues from HERING Bahnbau have been working on finishing up the project at the Niederrad construction site since December 2023. A complex undertaking on a large construction site: It was necessary to make tamping equipment available in the period from December to the end of January. Manual replacement measurements were carried out and alarm values eliminated within the scope of this work. There was also still some work to be done in relation to the noise barriers: Soil excavation, installation of KG2 as a side path and the removal of the remaining size II cable ducts were on the to-do list.
The underground cable construction work also accompanied us throughout the entire construction phase: While the remaining tasks are being carried out, concrete cable ducts are also being installed as well as uncovered and re-covered and old cables are being dismantled while others are being relocated.
This construction project is expected to be completed at the end of May 2024.