Bridge sleeper replacement in Baal-Lindern

The Baal-Lindern construction project is a project from 2014 during which Hering replaced the track section on a length of 3,694 m. This refurbishment section contains four structures where in 2014 – due to the lack of provision of the B100 sleepers – the superstructure had to be completed with the existing sleepers. The renovation of 494 sleeper units on the four structures was undertaken in the period from 8 – 18 June 2015 in night shifts with an additional shutdown period from 11.15 p.m. – 5 a.m.

Two de-loading cuts were made on each structure and the sleepers were replaced in six shifts with a net working time of 4 hours in parallel with two crews working head-on. Each crew was equipped with two, two-way excavators and seven workers. After the sleeper replacement, a tampering machine was used to tamper the sleepers in two tamping processes. The sleepers were subsequently released for train travel up to 80 km/h.

As soon as the sleeper replacement was fully completed on a structure, the second stabilisation process was carried out across the entire structure. After the replacement of 494 sleepers was fully completed, the tracks were neutralised and welded on the structures.



Always be up to date with the HERING newsletter!

Exhibitions / Events

Newsletter IconNewsletter