In addition to the track construction work on the line Waldfriedhof - Rheinlandstraße (Lots 1+2), HERING also realised the reversing loop project (Lot 3) for VGF in September and October 2017.
The installation of a reversing loop with a radius of 22 meters is considered a special challenge and a central achievement of this project. In addition, for example, 165 m of grooved track were renewed and over 1,000 tons of frost protection material was installed.
Further details can be found on the construction site sign.
Stadtwerke Verkehrsgesellschaft Frankfurt a.M. mbH
25/09/2017– 28/10/2017
Approx. € 570,000
Renewal of four grooved rail switches EW-60R1-50-RSP
Renewal of 165 m of grooved rail
Installation of 1,050 t antifreeze material
Supply and installation of 165 m Rheda-City-D ballastless track system for track 60R1
Installation of a turning loop with a radius of 22 meters
Installation of a concrete base plate C30/37 in a thickness of 30 cm
270 m³ concrete
Poured in 290 m track and points bottom sections
Various civil engineering works
Several hundred meters of cable conduit systems with shafts and a new drainage system