VGF Ffm Waldfriedhof – Rheinlandstraße

Extensive track construction work was scheduled for Hering in autumn 2017 in the Frankfurt city area. The service portfolio here ranged from track renewal (> 2 km) to the installation of more than 3,000 concrete sleepers and the laying of over 300 rails measuring 15 metres in length.

The special challenge: a nature reserve in the immediate vicinity of the construction site and, among other things, extremely high demands on logistics.

Further details can be found on the construction site sign.

Construction panel

Waldfriedhof – Harthweg (Lot 1)
Harthweg – Rheinlandstraße (Lot 2)


Client:

Stadtwerke Verkehrsgesellschaft Frankfurt a.M. mbH

Completion period:

25/09/2017– 28/10/2017

Order volume:

€ 1,660,000

Scope of services:

  • Renewal of 2.365 km of track
  • 8,860 m² explosive ordnance and bomb detection
  • 3,600 m² installation of geosynthetics
  • 5,600 m² soil replacement in various areas
  • 8,860 m² installation of antifreeze layer
  • Installation and removal of a total of 3,140 concrete sleepers and over 300 rails, each 15 m long  
  • Manufacture of 228 welds
  • Tamping work (over 2.4 km track)
  • Removal, transport and disposal of 13,200 tons of old ballast and soil material
  • Supply and installation of 13,200 tons of frost protection material and new gravel

Particularities:

Nature reserve in the immediate vicinity creating, among other things, special logistical challenges 

HERING reference projects:

Track construction with HERING

  • One-stop comprehensive solutions
  • Alternative products and construction methods
  • Individual solutions and immediate measures